Please take note of the following important dates and deadlines related to the PeopleTools upgrade:
* Now through 4/23 Add your ID to the provided link to ensure your account is unlocked for testing and validation. NeSIS Home - PT861 Upgrade Testers/Checked Out Users for PRD Validation<https://urldefense.com/v3/__https://uofnebraska.sharepoint.com/sites/Enterpr... >
* 4/21 (Monday) Deadline to request additional testing time or report any issues meeting the signoff timeline.
* 4/23 (Wednesday) at 12:00 PM Signoff to Production is due. All validations in DEV / TST / QA instances must be completed by this time.
* 4/23 (Wednesday) at 2:00 PM Planned Phire- Mod Review meeting and Cancellation of Production batch processing in preparation for the upgrade on 4/25.
* 4/25 (Friday) 6:00 PM – Production batch jobs processing shuts down. 8:00 PM – All Production systems Mavlink, MyRed, MyRecords, MyBlue, MyNCTA, MyCSC, MyPSC, Wildcatsonline NeSIS systems will go down @8:00pm for PT 8.61.10 upgrade .
* 4/26 (Saturday)
6:30 AM – Upgrade activities expected to be completed. 7:00–8:00 AM – Internal NeSIS validation. 8:30 AM–12:00 PM – Campus-level validation. Campus Validation to begin no later than 8:30am, NeSIS Zoom4 - # 810-280-151 - open during validation. <https://urldefense.com/v3/__https://nebraska.zoom.us/j/810280151__;!!PvXuogZ... > 12:00 PM – Final signoff deadline. Campuses signoff to open Production to all users (SharePoint Signoff) CSC – Joby, PSC – Deb Haveman, WSC – Jeremy N, UNK – Kim Seitler UNL/NCTA - Scott Krienert, UNMC – Paulo Shila, UNO – Matt S Click to Signoff https://urldefense.com/v3/__https:/uofnebraska.sharepoint.com/sites/EnterpriseServices/nesis/nesishome/_layouts/15/listform.aspx?PageType=8&ListId=*7bDA032F9E-9D0E-4258-99FB-5924C84D5839*7d&RootFolder=*sites*EnterpriseServices*nesis*nesishome*Lists*PT859*20Open*20PRD*20Signoff&Source=https*3a**Auofnebraska.sharepoint.com*sites*EnterpriseServices*nesis*nesishome*Lists*PT859*2520Open*2520PRD*2520Signoff*AllItems.aspx&ContentTypeId=0x010088803986336E2846A22B258392B9037A__;JSUvLy8vLy8lJSUlLy8vLy8vLy8lJSUv!!PvXuogZ4sRB2p-tU!BZ7sXUJldobvgmJToJiTsPJpiZ2jpy7aQSTGy2GAU2IEKNDd72gf865vq13j3nixQIt8H9JJNa4GWB7FPvvTE28S32b2$ 2:00 PM – All accounts unlocked and batch processing resumes.
Please let us know if you have any questions.
Thanks, Saranga
There are about 25 issues were submitted during PT 861 testing, of which 24 have been resolved. One issue is currently pending a response from the customer. AMP will follow up with the FCs tomorrow morning to check if any campuses have requested additional time for testing or sign-off.
Let us know in case of any questions.
Thanks, Saranga